Performance Test for Cerro Dominador CSP Power Plant

Chile - María Elena
Gekoppelde oplossingen
Klant Cerro Dominador CSP
Locatie María Elena, Maria Elena, Región de Antofagasta, Chile
Periode 2021
Capaciteit 113MW

Project Description:

Performance tests for the Cerro Dominador power plant. Renewable generation plant, based on a concentrating solar power tower with a steam cycle with installed capacity of 113 MW.

Services Provided

Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ASME PTC 46 and ASME PTC 6.