  • Multi-purpose hydro scheme (€1.2bn)
  • 500 kV XLPE cables and OHLs (€600m)
  • Development of grid-integration strategy
  • Simultaneous start-up of plant & grid
  • Grid-synchronisation at 350 km distance
  • Risk of blackout due to high ratio unit capacity (250 MW) to grid load (800 MW)
Klant 1,250 MW Merowe 500 kV AC grid
Locatie Merowe dam, Sudan
Periode 2005 - 2013
Capaciteit 250 MW

Gerelateerde expertise

De gerelateerde expertisedomeinen zijn:
Dams Submarine, Underground and Cables Smart Grids and Advanced Metering Systems