Modern locks for the world's busiest artificial shipping lane

25 Mar 2022

With the passage of 90 ships each day, the Kiel Canal in Germany is a key element of the trans-European transport network. Our experts are planning the modernization of the Kiel-Holtenau locks during ongoing operation.

As the busiest artificial sea route in the world, the 98-km Kiel Canal plays an important role in freight traffic. It has connected the North Sea and the Baltic Sea since the end of the 19th century, and now averages 90 ships a day and 100 million tons of goods per year.

One of two approaches to the canal is the Kiel-Holtenau lock. It consists of two locks. Currently, only the larger lock (310 m long by 42 m wide) is operational, as the smaller one is under construction. But there is also a need to modernize the large lock.

The Kiel Canal Construction Authority commissioned our experts from Tractebel Hydroprojekt in Magdeburg, Germany to plan a new sluice drive variant to be used for the entire lock system. The task is to develop a new drive by the end of 2025 that is reliable, fail-safe and low-maintenance. The concept will provide for two drives for each lock gate so that replacements are available at all times in the event of a malfunction.

New sluice drives will improve the entire lock system

Preliminary investigations during operation

For the planning phase, our experts examined the specifications of the existing plant dating from 1967 and compared them with measurement data from ongoing operations. The findings form the basis for further planning steps.

A main challenge during these preliminary investigations is to keep the lock operational with minimal downtime. To accomplish this, our experts called on measurement specialist Althen Sensors & Controls. Althen developed and carried out project-specific individual measurement solutions to determine, for example, exact load peaks. These real measured values serve as a basis for precisely dimensioning the new sluice drives and identifying and eliminating any problems that may arise during the planning phase.

Our experts are currently drawing up the approval documents for the construction phase. They will then prepare the tender documents and advise the client throughout the Europe-wide bidding process.

The Kiel Canal, the busiest artificial sea route in the world

"A smoothly functioning waterway between the North Sea and the Baltic Sea means shorter and therefore more environmentally friendly transport routes. We are planning a modern, durable, energy-efficient and fail-safe operation that uses eco-responsible lubricants and can perform its task reliably and effectively."

Tobias Schaulat, project engineer

Discover our hydraulic infrastructure solutions

 

Gerelateerd nieuws

AH_PVT_Crop_2a

Tractebel welcomes new CEO

Tractebel announces that Anne Harvengt stepped into the role of Chief Executive Officer on May 1, 2024

Lees verder
02 May 2024
Banner_photo

Hydroelectric project in India sets two world records

The 960 MW Polavaram hydroelectric project provides hydropower, irrigation, and drinking water to five regions across India’s...

Lees verder
23 Apr 2024
Tanahu_Ceremony_at_tunnel_2

Tunnel breakthrough a key milestone in 140-MW hydropower project in Nepal

Nestled among the towering Himalayas west of Kathmandu, the Tanahu hydropower project reached a major milestone on March 31, 2024: the breakthrough of the 1.4-km...

Lees verder
19 Apr 2024
Cover_1

Listen to Engineering Angles, Tractebel’s podcast!

We caught up with Stéphanie Brine, Group Manager at Tihange nuclear power station in Belgium, to discuss her fascinating career path, her experience as a woman in...

Lees verder
02 Apr 2024