The 98 MW, natural gas-powered Nexif Ratch Energy Rayong power plant has entered into commercial operation in Rayong, on the east coast of the Gulf of Thailand. Tractebel acted as owner’s engineer.

April 30, 2022 marked the successful conclusion of a major new energy project for Thailand, reaching its commercial operation deadline as planned. As owner’s engineer of the project, Tractebel’s energy experts supported the engineering design review and project management.

The 98 MW Nexif Ratch Energy Rayong (NRER) combined-cycle power plant project includes the world’s first 62 MW SGT-800 gas turbine and Thailand’s first 36 MW SST-600 steam turbine. The project is considered an important step in the move towards cleaner energy in Thailand, as natural gas is more efficient and produces significantly less emissions than petroleum or coal. The NRER power plant is among the most energy-efficient of its kind.

The 98-MW Nexif Ratch combined-cycle power plant in Rayong, Thailand

Nexif Ratch Energy Rayong Company Limited has entered into a 25-year Small Power Producer agreement to supply 90 MW of electricity to the Electricity Generation Authority of Thailand. The project is located in the SPP Industrial Park, Rayong, Thailand.

“Despite the challenges we encountered along the way – including COVID-19 and the Russia-Ukraine conflict – all parties put in their best efforts and met the commercial operation date target. We would like to congratulate NRER for this great achievement, which will go a long way towards reducing harmful emissions in Thailand.”

Suparerk Wangtiprak, Tractebel Project Manager

Discover our Power & Heat solutions

 

 

Gerelateerd nieuws

Banner_photo

Hydroelectric project in India sets two world records

The 960 MW Polavaram hydroelectric project provides hydropower, irrigation, and drinking water to five regions across India’s...

Lees verder
23 Apr 2024
Tanahu_Ceremony_at_tunnel_2

Tunnel breakthrough a key milestone in 140-MW hydropower project in Nepal

Nestled among the towering Himalayas west of Kathmandu, the Tanahu hydropower project reached a major milestone on March 31, 2024: the breakthrough of the 1.4-km...

Lees verder
19 Apr 2024
Cover_1

Listen to Engineering Angles, Tractebel’s podcast!

We caught up with Stéphanie Brine, Group Manager at Tihange nuclear power station in Belgium, to discuss her fascinating career path, her experience as a woman in...

Lees verder
02 Apr 2024
PANT01_project_image_240318

Designing a medical radioisotope production facility for cancer treatment

Jointly with its partner, MODULO architects, Tractebel will combine its infrastructure and nuclear expertise to support the design and construction of PanTera's actinium-225...

Lees verder
28 Mar 2024