Green energy in abundance: Adding 456 MW of commercial production from the Upper Tamakoshi hydropower plant to the national grid enables Nepal to generate an energy surplus during the wet season. Our experts took over the implementation planning and construction management.  

The Upper Tamakoshi Hydroelectric Project (UTKHEP) is a prestigious milestone in the energy transition in Nepal. The plant is located in a remote region of the upper Himalayas on the Tamakoshi River basin, about six kilometers from the border with Tibet. With a natural head of 822 m and six underground units, it produces up to 2,281 GWh of electricity annually. This renewable energy will improve living conditions and promote economic development in the country.

All six turbines and generators have been in full operation since September 2021. During the rainy season, the total electricity generation of Nepal will exceed what the population and the economy are currently consuming. The whole country can benefit in several ways from the surplus of electricity: Electricity costs will decrease and there are plans to supply consumers in need with electricity free of charge. In addition, Nepal could export electricity.

Expansion considered

The Nepal Electricity Authority, Nepal Telecom, Citizens Investment Trust and Rastriya Beema Sansthan are the promoters of Upper Tamakoshi Hydropower Limited (UTKHPL). The general public has also made a huge investment through the company’s initial public offering (IPO). The UTKHPL, executing agency of the plant, is considering a second expansion stage, the Rolwaling Khola Hydroelectric Project (RKHEP) with an installed capacity of 20 MW. In addition to the 2,281 GWh annual energy from the UTKHEP, another 105 GWh would come from this new power plant.

Since 2011, our hydropower experts have been responsible for the implementation planning and construction management of the project, in cooperation with our partners. Our experts were involved in monitoring and planning as well as in construction contract management. They reviewed the design of the transmission line and inspected the construction activities for all structures. Despite the difficult terrain and major damage to the construction sites caused by the severe earthquake of 2015, the project team has rigorously followed its objective of meeting completion deadlines.

Hydroelectric energy is one of the sustainable renewable energies with low-carbon emissions. The use of hydropower as the main source of energy for everyday activities will help to noticeably reduce fossil fuel carbon emissions in Nepal”, says Swochhendra Rokka, Project Coordinator.

 

Discover more about our Hydro Solutions

Gerelateerd nieuws

Cover_1

Listen to Engineering Angles, Tractebel’s podcast!

We caught up with Stéphanie Brine, Group Manager at Tihange nuclear power station in Belgium, to discuss her fascinating career path, her experience as a woman in...

Lees verder
02 Apr 2024
PANT01_project_image_240318

Designing a medical radioisotope production facility for cancer treatment

Jointly with its partner, MODULO architects, Tractebel will combine its infrastructure and nuclear expertise to support the design and construction of PanTera's actinium-225...

Lees verder
28 Mar 2024
AdobeStock_383755906

Powering data centres with advanced nuclear technologies

Tractebel and its subsidiary company RED published a White Paper on how Small Modular Reactors (SMRs) can provide zero-emission, reliable, and sustainable energy to data...

Lees verder
06 Mar 2024
Photo_1

Nepal’s largest hydroelectric plant to add 1,061 MW to the national grid