Client | Prime Energía |
---|---|
Emplacement | Diego de Almagro, Región de Atacama, Chile |
Période | 2019 |
Capacité | 74MW |
Performance tests for Units I and II of the Emelda power plant, a backup generation plant consisting of two gas turbines fueled by diesel. Each unit is rated at 37 MW.
Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ASME PTC 22 and ISO 2314.