Performance Test for Santa Marta Power Plant

Chile - Talagante
Solutions associées
Client Consorcio Santa Marta
Emplacement Talagante, Región Metropolitana, Chile
Période 2021
Capacité 20MW

Project Description:

Performance Test for Santa Marta power plant. Santa Marta is a Renewable Energy plant conformed by 10 generator sets (10 Caterpillar biogas motors of 2 MW each) that burns waste gas produced in the adjacent landfill.

Services Provided

Realization of performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ISO 3046 and ISO 15500.