Performance Test for Cardones Generation Plant

Chile - Copiapó
Linked solutions
Client Inkia Energy
Location Copiapó, Atacama, Chile
Period 2017 and 2021
Capacity 155 MW

Project Description

Performance tests the Cardones power plant, a backup generation plant consisting of one gas turbine fueled by diesel.

Services Provided

Performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ASME PTC 22 and ISO 2314.