Client | Imelsa |
---|---|
Location | Copiapó, Atacama, Chile |
Period | 2022 |
Capacity | 5 MW |
Performance tests for the Cenizas power plant, a backup generation plant consisting of one diesel generator.
Performance test required by the Chilean independent grid operator, Coordinador Eléctrico Nacional. Testing methodology according to ISO 3046 and ISO 15500.