Mantaro Hydroelectric Complex Modernisation

Peru
Solutions associées
Water

Mantaro Hydroelectric Complex, located in the region of Huancavelica, began its operations in 1973, and includes installations of Tablachaca Reservoir located in the town of Quichua, with dam capacity of 8 million m3. There the water from the river Mantaro is stored, and through a tunnel of 19,8 km derived the waters to the turbines of the seven generators of the 798 MW Santiago Antunez de Mayolo Hydroelectric Power Plant . The water is conducted by a waterfall at three turbines of 210 MW capacity of the Restitution Hydroelectric Power Plant.

Client Electroperu
Emplacement Mantaro River, Peru
Période 2015-2017
Capacité 1,008 MW

Services provided

Sous-domaines utilisés

Introduction aux sous-domaines utilisés
Hydropower Plant Rehabilitation & Upgrade Large Hydropower Projects