1,250 MW Merowe 500 kV AC grid

Sudan
Solutions associées
Water
Energy
  • Multi-purpose hydro scheme (€1.2bn)
  • 500 kV XLPE cables and OHLs (€600m)
  • Development of grid-integration strategy
  • Simultaneous start-up of plant & grid
  • Grid-synchronisation at 350 km distance
  • Risk of blackout due to high ratio unit capacity (250 MW) to grid load (800 MW)
Client 1,250 MW Merowe 500 kV AC grid
Emplacement Merowe dam, Sudan
Période 2005 - 2013
Capacité 250 MW

Sous-domaines utilisés

Introduction aux sous-domaines utilisés
Dams Submarine, Underground and Cables Smart Grids and Advanced Metering Systems

Références liées