The 132 kV Solu Corridor transmission line provides electricity to three remote districts in northeastern Nepal. Our experts from Tractebel in India provided project management consulting services for the transmission line and substation project.

The 90-km long, 132 kV double-circuit Solu Corridor transmission line and 132/33/11 kV substation at Tingla in Nepal are now operational. The transmission line, which crosses areas of high altitude and challenging terrain, evacuates power generated by hydroelectric plants on the Solu River in the Solukhumbhu district to the national grid.

Tractebel’s energy experts in India have been involved in the initiative since 2014, when they were appointed as Project Management Consultant by the client Nepal Electricity Authority (NEA). The project was funded by the Government of Nepal and the Export-Import (EXIM) Bank of India.

The Solu substation near the village of Tingla, northeastern Nepal

Connecting rural Nepal to the national power grid

The 132 kV Solu Corridor transmission line project connects the remote Solukhumbhu, Khotang and Okhaldhunga districts of northeastern Nepal with the national electricity grid via the new 132/33/11 kV substation near the village of Tingla and the existing 132/33/11 kV substation at Mirchaiya. It is a significant socio-economic development in this rural and remote part of Nepal, in addition to contributing to the country’s overall economic and industrial progress.

Tractebel has been involved with the Solu transmission line and substation project since 2014.

Joint collaboration strengthens international ties

Indian Prime Minister Narendra Modi and Nepalese Prime Minister Sher Bahadur Deuba jointly inaugurated the 132 kV Solu Corridor transmission line from New Delhi, India, virtually, on April 2, 2022. Further reinforcing Indo-Nepalese relations, the project is one of many supported jointly by the two countries.

The Nepalese and Indian Prime Ministers jointly inaugurated the 132 kV Solu Corridor transmission line in New Delhi, India, on April 2, 2022

“Nepal’s hydropower capacity is rapidly growing, and our teams are pleased to play a role in delivering that power to the national grid. The Solu transmission line will benefit both regional and national economies, as a portion of the energy generated will be delivered to other regions in the country. Since the electricity is derived from hydropower, it contributes to the energy transition away from fossil fuels.”

Haraprasad Biswas, Tractebel Team Leader

Explore our Power Transmission & Distribution Solutions

 

 

 

Actualités liées

Cover_1

Listen to Engineering Angles, Tractebel’s podcast!

We caught up with Stéphanie Brine, Group Manager at Tihange nuclear power station in Belgium, to discuss her fascinating career path, her experience as a woman in...

Trouver plus
02 Apr 2024
PANT01_project_image_240318

Concevoir une installation de production de radio-isotopes médicaux

Avec son partenaire MODULO architects, Tractebel combinera son expertise en matière d'infrastructure et de nucléaire pour soutenir la conception et la construction de...

Trouver plus
28 Mar 2024
AdobeStock_383755906

Powering data centres with advanced nuclear technologies

Tractebel and its subsidiary company RED published a White Paper on how Small Modular Reactors (SMRs) can provide zero-emission, reliable, and sustainable energy to data...

Trouver plus
06 Mar 2024
Photo_1

Nepal’s largest hydroelectric plant to add 1,061 MW to the national grid

Powering the future of Nepal: Plans for the monumental Upper Arun hydropower project will be set in motion in March 2024. Our experts will oversee every phase of the...

Trouver plus
01 Mar 2024