India’s largest rubber dam creates waterfront at sacred site

22 Nov 2022

An ingenious solution conceived and designed by Tractebel engineers has brought a sacred river to the surface in Bihar state, India.   

For followers of the Hindu faith, the city of Gaya in the eastern Indian state of Bihar is an important pilgrimage site. A focal point is the Vishnupad temple on the bank of the Falgu River, where people come to pay homage to their ancestors. The problem was that the river flowed mostly underground. For many years, pilgrims had to dig deep into the sand to draw the water needed for religious rituals. 

The Government of Bihar called upon Tractebel to find an engineering solution. The goal was to ensure a year-round “waterfront” next to the Vishnupad temple. Tractebel carried out comprehensive integrated surface-ground water modelling and water balance studies, and proposed a rubber dam across the Falgu River. It would be the first of its kind in the region, and the largest rubber dam in India.  

Before

After

A detailed project report of the concept and design was submitted, approved, and construction undertaken. Now, the completed project is a reality and was inaugurated by the Chief Minister of Bihar on September 8, 2022.

   

“The rubber dam was the most appropriate engineering solution for many reasons, including environmental concerns,” says Mithilesh Kumar, Tractebel Associate Vice President - Water, India. “In terms of the power requirement to operate the rubber dam, it is significantly lower than hydraulic gates on a conventional dam. The project will also enhance ground water availability and reduce the scarcity of drinking water to some extent. The successful design and implementation of this project not only ensures year-round water availability in the river near the temple, but it also greatly enhances the aesthetic, cultural and religious value of the area. It is expected to increase tourist and pilgrim influx as well as length of stay in the city, which will boost the local economy.”  

Mithilesh Kumar, Tractebel Associate Vice President - Water, India 

 

 

Actualités liées

Tanahu_Ceremony_at_tunnel_2

Tunnel breakthrough a key milestone in 140-MW hydropower project in Nepal

Nestled among the towering Himalayas west of Kathmandu, the Tanahu hydropower project reached a major milestone on March 31, 2024: the breakthrough of the 1.4-km...

Trouver plus
19 Apr 2024
Cover_1

Listen to Engineering Angles, Tractebel’s podcast!

We caught up with Stéphanie Brine, Group Manager at Tihange nuclear power station in Belgium, to discuss her fascinating career path, her experience as a woman in...

Trouver plus
02 Apr 2024
PANT01_project_image_240318

Concevoir une installation de production de radio-isotopes médicaux

Avec son partenaire MODULO architects, Tractebel combinera son expertise en matière d'infrastructure et de nucléaire pour soutenir la conception et la construction de...

Trouver plus
28 Mar 2024
AdobeStock_383755906

Powering data centres with advanced nuclear technologies

Tractebel and its subsidiary company RED published a White Paper on how Small Modular Reactors (SMRs) can provide zero-emission, reliable, and sustainable energy to data...

Trouver plus
06 Mar 2024