Tamakoshi reservoir secures power supplies in Nepal

02 juil. 2020

Implementation of Nepal’s largest hydropower project is approaching the finishing line: the Upper Tamakoshi reservoir was filled for the first time. The plant will increase the country’s electricity generation capacity by around 60%, thereby eliminating current shortfalls in the power supply system.  

Implementation of Nepal’s largest hydropower project is approaching the finishing line: in March 2020 the Upper Tamakoshi reservoir was filled for the first time. Once regular operation of the plant commences, it will increase the country’s electricity generation capacity by around sixty percent, thereby eliminating current shortfalls in the power supply system.  The joint venture between Tractebel Germany (formerly Lahmeyer International) and Norconsult AS has been responsible for the detailed planning and construction management of the project since 2011.

The plant is located in a remote region of the upper Himalayas, in the Tamakoshi river basin, about six kilometres from the border with Tibet. Featuring six underground turbine units, it is expected to generate 2.3 TWh of urgently needed electricity – the project is therefore a high national priority.

Despite the difficult terrain and the major damage to the construction sites caused by the severe earthquake of 2015, 99 percent of the work has now been completed. Even under these difficult circumstances the project team has rigorously followed its objective of meeting completion deadlines.  One key milestone was successfully accomplished in March 2020 when the reservoir, with a storage capacity of 1.2 million m3, was filled with water for the first time.  This means that the dam and its appurtenant structures for the 456 MW peak load hydropower plant are now ready for the required technical tests.

Testing dam operation 

Following the seven-day impoundment phase, power plant specialists commenced the testing programme in order to evaluate and confirm the dam functionality along with its auxiliary structures.  The tests will determine whether structures comply with their design standards, assure the dam’s functionality, and verify the reliable operation of the sedimentation basins and the various mechanical equipment items.  As a consequence of the current Covid-19 pandemic, and in order to ensure the health and safety of the people working on site, test activities are currently proceeding at a relatively slower pace.

Once the tests are successfully concluded, the reservoir will be emptied again to allow any rectification works to be carried out.  “We hope that we will soon be able to resume our work with maximum efficiency, so that we can achieve our Project objectives as quickly as possible and deliver a Project of such importance to the Nepalese people and for the economic development of the country,” says Renos Christakis, senior geologist at Tractebel.

Discover more about our Water Solutions

A strategic energy supply will soon be connected to the grid.  Prior to this, the dam of this hydropower project in the Himalayas is to undergo a series of technical tests.

Actualités liées

adobestock_57853569_1

Tractebel Ice Fall Risk Assessment Digital Application

Our innovative experts have developed the first cloud-based web application for ice fall risk assessment for wind projects. Thanks to this methodology our customers can now...

Trouver plus
23 sept. 2020
GERD_Ethiopia2020

Ethiopia: First stage of the filling of the reservoir of the Grand Renaissance Dam

The Grand Ethiopian Renaissance Dam project is part of the Country development and transformation programme that was defined by the Ethiopian government in the early 2010's....

Trouver plus
10 sept. 2020
port_ostende_1

Les travaux d'élargissement du chenal du port d'Ostende progressent bien

Les travaux de construction dans le port d’Ostende, designé par Tractebel, progressent bien malgré les mesures liées au COVID-19. Le consortium Jan De...

Trouver plus
21 août 2020
AdobeStock_181922208

Turkey’s wind & wave future perfectly mapped

Wind turbines and wave power generators generate renewable energy worldwide. Now our experts have examined the wind and wave energy potential all around Turkey.

Trouver plus
20 août 2020