The plant includes biological treatment by activated sludge and fine bubble aeration, sludge digestion and energy recovery, odour control, as well as the complete complementary infrastructure. The construction covers the complete turn-key execution of civil works and electro-mechanical installations, as well as the commissioning of the plant.
Client | Empresas Públicas de Medellín |
---|---|
Location | Medellín, Antioquia, Colombie |
Period | 2006 - 2018 |
Capacity | Average flow 5.0 m³/s for 2.75 million PE |
With the trusted expertise of GKW Consult