This project encompasses a ±500 kV direct current power transmission line (> 1,000 km), the construction of two substations, two ground electrode stations and connection of the 400 kV AC substations to the national power grids.
Client | KETRACO and EEPCO |
---|---|
Location | Ethiopia - Kenya |
Period | 2013-2017 |
Capacity | ±500 kV direct current power transmission line (> 1,000 km) |